[DC Flag]
GOVERNMENT OF THE DISTRICT OF COLUMBIA

Advisory Neighborhood Commission 3B
Glover Park/Cathedral Heights
P.O. Box 32312
Washington, DC 20007
phone: 202-338-2969
fax: 202-333-8654
anc3b@aol.com
Blue Bar
ANC 3B Home
About ANC 3B
ANC 3B Commissioners
ANC Citizen Charter
ANC 3B Map
Links
Road Construction Update
Subscribe to ANC 3B Mailing List

April 10th , 2003

Glover Park Road Construction began on Monday, October 7th. It was originally scheduled to be completed by Tuesday, January 7th, 2003. This schedule, however, has changed. Most of the work on streets to be reconstructed or upgraded has been delayed.

Resurfacing of Glover Park Streets is currently underway and will be completed by the end of 2002. Resurfacing includes milling and overlaying roadway surface with new asphalt, replacing portions of curbs, gutters, sidewalks, alleys, wheelchair ramps, catch basins (storm drains) as well as upgrading streetlights and tree plantings.

Replacement of Catch Basins and Storm Drains throughout Glover Park is also currently underway and will be completed during the first quarter of 2003.

Reconstruction and Upgrading work will be re-scheduled for Spring 2003 when weather conditions are likely to be more favorable. Reconstruction is an extension of resurfacing work and includes installing a new roadway base and asphalt surface. Upgrading is similar to reconstruction but also includes widening some roadways as well as installing curbs and gutters where they do not exist.

Status:

  • The new sewer system on 42nd Street (2300-2500 blocks) will be installed beginning the week of March 17th.
  • Curb, gutter, and sidewalk work began on W Street and 42nd Street between 40th Street and Tunlaw Road the week of March 24th.
  • Landscapers will work as weather permits but no trees will be planted before Spring. Work is currently underway on Davis Place (3900-4000 blocks).
  • ROADWAY EXCAVATION AND CONSTRUCTION RESUMED THE WEEK OF MARCH 17th. (RAIN DELAYS THE WEEK OF APRIL 7th HAS CAUSED DELAYS.)

    • Work will begin in the 3900 to 4100 blocks of Edmunds Street on March 19th. The street will be closed during the day. Buses will be re-routed from 41st Street, left on to Davis, right on to 42nd, right on to Tunlaw, right on to 39th and then resume their normal routes.
    • The week of March 24th, work will begin on the 3800 Block of Davis Place and then proceed to the 3900 to 4000 blocks.
    • As work nears completion on Davis Place, work will begin on the 2300 to 2600 blocks of 41st Street.
    • The final phase of excavation/reconstruction work will be on W Street/42nd Street from 40th Street to Tunlaw Road.
    • Each phase of road construction is expected to take roughly two weeks to complete.

Notification: The D.C. Department of Transportation is required to notify effected residents in writing at least six days in advance of the beginning of any roadwork.

SCHEDULE

Street Resurfacing to be Completed

  • 41st Street: Calvert Street to Benton Street
  • Benton Street: 41st Street to 40th Place
  • 38th Street, W Street to Benton Street
  • 40th Place: Beecher Street to Benton Street
  • Huidekoper Place: Cul-de-sac to Beecher Street
  • W Street: Observatory Place to 40th Street

Streets to be Resurfaced

  • 39th Place: Calvert Street to W Street
  • Observatory Place: W Street to Beecher Street

Streets to be Reconstructed

  • 41st Street: Davis Place to Edmunds Street
  • Beecher Street: 39th Street to Tunlaw Road
  • Davis Place: 41st Street to Tunlaw Road
  • Edmunds Street: 39th Street to 42nd Street

Streets to be Upgraded

  • 40th Place: Beecher Street to Calvert Street
  • 40th Place: W Street to Benton Street
  • 40th Street: Park Property Line to Benton Street
  • 41st Street: Davis Place to Calvert Street
  • 42nd Street: W Street to Tunlaw Road
  • Manor Place: 37th Street to Huidekoper Place
  • Observatory Place: Manor Place to W Street
  • W Street: 40th Street to 42nd Street

Staging Area for Road Construction Equipment: 42nd and Davis Place from Behind the Stop Sign to the Entrance to the Park; Beecher and 42nd Street; W Street along the park line; and 41st and Davis Place.

Parking: Fort Myer Construction (the contractor) will return as many on-street spaces for parking as possible for the evening and overnight hours. Please note that cars must be moved by 7 A.M. between Monday and Saturday or they will be towed. Tow trucks will move them to the first available space but will not be able to keep track of where each vehicle is moved.

PLAN OVERVIEW

For an overview of the plans, please link to dcroadwaysward3and4.com.

 

Map of Proposed Road Construction



Click on Map for Larger Image
Blue Bar

The Glover Park/Cathedral Heights ANC thanks Person-to-Person PC
for donating the initial design of this site.

This document was last revised on

[go back to DC Neighborhoods]