April 10th , 2003 Glover Park Road Construction began on Monday, October 7th. It was originally scheduled to be completed by Tuesday, January 7th, 2003. This schedule, however, has changed. Most of the work on streets to be reconstructed or upgraded has been delayed. Resurfacing of Glover Park Streets is currently underway and will be completed by the end of 2002. Resurfacing includes milling and overlaying roadway surface with new asphalt, replacing portions of curbs, gutters, sidewalks, alleys, wheelchair ramps, catch basins (storm drains) as well as upgrading streetlights and tree plantings. Replacement
of Catch Basins and Storm Drains
throughout Glover Park is also currently underway and will be completed
during the first quarter of 2003. Status:
Notification:
The D.C. Department of Transportation is required to notify effected residents
in writing at least six days in advance of the beginning of any roadwork.
Streets to be Resurfaced
Streets to be Reconstructed
Streets to be Upgraded
Staging Area for
Road Construction Equipment: 42nd and Davis Place from Behind the
Stop Sign to the Entrance to the Park; Beecher and 42nd Street; W Street
along the park line; and 41st and Davis Place. PLAN OVERVIEW
|
|
The Glover Park/Cathedral
Heights ANC thanks Person-to-Person PC
|
||